Construction Report 12/12/17

ConstructionConstructionStucco CrewPorch PrepBehind BuildingBack of Gym
Construction Report
Posted on 12/12/2017
Construction

As of today, the construction is moving along nicely.

Superintendent Steve Reynolds reports that almost the entire interior of the building has been lined in sheet rock, including the foyer area. Wall boards are being installed and texture applied, so the walls are really taking shape! The lights, goals, and air conditioning ducts will also be installed this week. The projected timeline for interior completion (apart from a beautiful gym floor) is February. 

The exterior of the building is ever-changing, as the brick and stucco teams race along with progress. The agriculture science building in particular looks completely different with the addition of a brick facade to match the other buildings. It appears that our school-wide dream of watching the class of 2018 walk the stage to pick up their diplomas in the new gym is easily a reality. 

In other renovation news, our FCS department appliances have come in, and will be installed this summer. 

Our beloved West Texas winds are bringing a lot of change to Adrian, and all for the better! Look for another construction update next week.

JC